Ceremony of THE PROJECT FOR IMPROVEMENT OF SUBSTATIONS
   AND DISTRIBUTION NETWORK (PHASE 2)

Ceremony was held at the new Ndera substation on September 27,2018, before completion of THE PROJECT FOR IMPROVEMENT OF SUBSTATIONS AND DISTRIBUTION NETWORK (PHASE 2).
Mr. Miyashita (Ambassador) from Embassy of Japan in Rwanda, Mr. Takada (director) from JICA Rwanda office, Ms. Germaine (Minister) from Ministry of Infrastructure, Mr. Weiss (CEO) from Rwanda Energy Group and other persons concerned participated in this ceremony.

Project Profile
Project Name: THE PROJECT FOR IMPROVEMENT OF SUBSTATIONS AND DISTRIBUTION NETWORK (PHASE 2)
Client: Energy Development Corporation Limited (EDCL)
Contractor: Nishizawa Limited
Content: 
1) Newly-established 110/15kv substation (Ndera substation)
2) 15kv distributor addition of 110/15kv substation (Gasogi substation)
3) Newly-established 110/15kv Switching Station (Kabuga,Murindi)
4) Construction of 110kV transmission line
5) Construction of 15kV distribution line

Installation of switchboard   33/11kV distribution line
               Ndera substation          Unveiling commemorative plate

     news27_04.jpg
Control room   Panel room

 news27_05.jpg    news27_06.jpg
 Main Transformer   Traditional dancing