HOME > Press Release > Rwanda/Kigali Plant Design, Supply, and Installation Procurement of Kigali Network system Strengthening for Rehabilitate and Upgrade Eight (8) Distribution Substations (Cabins).

Rwanda/Kigali Plant Design, Supply, and Installation Procurement of Kigali Network system    Strengthening for Rehabilitate and Upgrade Eight (8) Distribution Substations (Cabins).

《Project Background》
 In Rwanda, because of approximately 8% of its economic growth rates in recent years, the electricity demand has increased around 10% per year. Through this project, we will build new 8 distribution substations in Kigali city. We will contribute toward the stabilization of the electric supply and the improvement of the economy in Rwanda.

《Project Profile》
Project Name: Rwanda Electric Sector Strengthening Project
Project Fund: The World Bank
Client/Enduser: Energy Utility Corporation Limited (EUCL)
Contractor: Takaoka Engineering Co., Ltd.

《Main Items》
1. 15kV GIS
2. Distribution Transformer
3. SCADA RTU
4. Communication Equipment
5. Protection equipment 
6. MV underground cables
7. Installation works
8. Civil works

Site.1   Site.2
Substation Construction Site.1   Substation Construction Site.2