HOME > Press Release > The Republic of Malawi / Delivery of Power Transformer for The Project for the Improvement of Substations in Lilongwe City

The Republic of Malawi / Delivery of Power Transformer for 
    The Project for the Improvement of Substations in Lilongwe City

On June 28th 2023, 5 power transformers for the captioned project were delivered to 2 substations in Lilongwe city. On the same day, ESCOM held press conference at Bingu International Conference Center.

【For Kanengo Substation】
  ① 132/66/11 kV 50MVA Transformer 1 unit
  ② 66/33 kV 25MVA Transformer 1 unit
  ③ 66/11 kV 25MVA Transformer 1 unit


【For Old Town Substation】
  ① 66/33 kV 25MVA Transformer 1 unit
  ② 66/11 kV 25MVA Transformer 1 unit

 

We continue to implement the safety site work until the project completion March, 2024.

On-line news by local media (Malawi24)

ESCOM says upgrading of substations will improve electricity supply | Malawi 24 | Latest News from Malawi 



Africa Map.png   MicrosoftTeams-image.png
Transformer for Kanengo Substation

  Transformer for Old Town Substation
3.jpg   4.jpg
               Banner prepared by ESCOM             Press Conference held by ESCOM