HOME > Press Release > Guyana project signing ceremony

Contract sigining ceremony for Guyana project

<The Project for The Introduction of Renewable Energy and the Improvement of Power System>

Contract signing ceremony for this project was held on February 28th, 2019.

This tender was divided by 2 lots because the end-users are different.

We had awarded these 2 tenders with Mitsubishi Corporation as consortium.

The project outlines are as follows.

 

[GPL project] Lot1

- End-user: Guyana Power & Light Inc. (GPL)

- Contractor: The consortium of Mitsubishi Corporation and Takaoka Engineering Co., Ltd.

- Project period: February 28th, 2019 ~ June 30th, 2020

- Project outline:

(1) Introduction of reactive power compensator
(2) Procurement of electric power distribution materials

 

[CARICOM project] Lot 2

- End-user: Caribbean Community (CARICOM)

- Contractor: The consortium of Mitsubishi Corporation and Takaoka Engineering Co., Ltd.

- Project period: February 28th, 2019 ~ September 30th, 2020

- Project outline: 

(1) 400kW PV generation system
(2) 150kWh Battery system
(3) Building Energy Management System (BEMS)

 

Installation of switchboard   33/11kV distribution line
Contract signing by Suzuki (President)   Affiliating members for this project