HOME > Business > Republic of Cuba / Project for the Improvement of Power Supply in the Isle of Youth

Republic of Cuba / Project for the Improvement of Power Supply                          in the Isle of Youth

On Cuba's largest remote island, by installing the equipment necessary to stabilize the power system,
we aim to stabilize the power supply and promote the introduction of renewable energy in this country.

 

《Project Outline》

Project name: The Project for the Improvement of Power Supply in the Isle of Youth

Project Fund: Japan International Cooperation Agency (JICA) Grant Aid

End user: Unión Eléctrica de Cuba (UNE)

Main contractor: Consortium of Nishizawa and Toshiba Energy Systems

Our contract work: Design and procurement of 34.5/6.6kV equipment
                            Design and procurement of storage containers for batteries and PCS
                            Design and procurement of other related equipment
                            SV dispatch for site installation work