HOME > Business > The Project for Rehabilitation of Monrovia Power System (2016)

The Project for Rehabilitation of Monrovia Power System (2016)

《Background of the project》
Just because such a civil war lasting 14 years long, some part of infrastructure facilities were burn down in Republic of Liberia. Afterword, the rehabilitation is the most prioritized than any works else today. The project is the one of grant aids from Japanese government to the country that aims to build 2 Power stations of 5MW as Monrobia city rehabilitation project. In this project we were not only procuring but also undertook an installation work of diesel generators. We contributed to economy in the country. After the project has been done successfully, people could make their living standard much easier that before and the electricity supply has been stable.

《Project outline》
Project : Rehabilitation of Monrobia Power System
Client : Liberia Electricity Corp.
Site : Bush-rod island Power station, Momrobia
Outline of construction: 
  1) Engineering, Procurement and Installation of 5MW DEG x 2sets
  2) HFO Pipe lines, 22kV Switchgears, Transformers


  Site View of Power Station  

Commemorative Monument
 
  Site View of Power Station   Commemorative Monument  
  Diesel Oil Storage Tank   Diesel Generating Set  
  Diesel Oil Storage Tank   Diesel Generating Set  
  Afternoon of National Staff      
  Afternoon of National Staff